技術(shù)文章
Technical articles第1步,石英管縮頸
抽真空后開始燒結(jié)縮頸,縮頸部位燒至凹陷即可
Step 1: Silica tube necking
Frit the necking after the vacuumizing until the necking part gets sunken
第2步,裝樣裝石英柱
將樣品裝入石英管,將石英柱下滑至縮頸處卡住
Step 2: Silica column sample loading
Put the sample into silica tubes and slide the silica column to the necking
for locking
第3步,燒結(jié)封管
抽真空充氣氛后,燒結(jié)石英柱的位置進(jìn)行真空封管
Step 3: Fritting and sealing
Frit the silica column and conduct tube sealing after the vacuumizing and gas atmosphere filling
封管成品
封管完成后可以貼上樣品標(biāo)簽以便于區(qū)分樣品
Sealing and completion
Paste the sample label to identify samples after the completion of tube sealing